Fractional Operator's Certification Information Page
Certification Preparation
Their are a number of things that you should do in order to prepare you for certification. Not to mention that reviewing this now will save a lot of time during the process. The list below will help you get on your way to an uneventful process, and the reading should be done by all first time Management Personnel.
Part 91 Reference Documents
| Title |
Description |
| Inspectors Handbook |
Information the FAA inspectors use as a guide during certifications. |
| 14 CFR Part 91 |
Copy of the Federal Aviation Regulations, Sub K is located at the end. |
| Advisory Circular |
Advisory Circular regarding Fractionals |
ACCG Creates Your Manuals & Gets FAA Approval ASAP!
Should you desire for us to make your manuals for you call 561-373-5962 or email for a quote.
Some FAA Certification Notes
- Review the appropriate sections of the Inspectors Handbook regarding new certifications. The Inspectors perform many other duties, and quite often have completed few new certifications. Your knowledge of the procedures will help.
- Remember the actual procedures will vary from FSDO to FSDO and from Inspector to Inspector.
- We have found that most inspectors follow the procedures outlined in the Inspectors Handbook, while some use the Gate System. The important thing is to learn how your inspector wants things done, and then do it that way. We have found that it rarely pays off arguing with the inspector.
- Stay on top of it. Don't hesitate to call your inspector if you don't here from him (or her). Quite often, due to reasons unknown, phone calls will not be returned so you will have to keep calling until you get what you need.
Required Manuals for Operations
Program Operating Manual (POM)
This manual contains information about your general policies, duties, responsibilities of personnel, operational control policy, and procedures. Part 91, subpart K requires that your manuals include instructions and information that allow your personnel to perform their duties and responsibilities.
ACCG will work closely together with the Program Manager and develop the procedures for your specific operation.
Part 91 Application Process for Part
91 Subchapter K
Below is a summary of the Fractional Program application process. Variations
will exist by operator size and complexity. The information is extracted from the latest draft of the the Fractional's certification advisory circular, additional detail may be found at http://www.faa.gov.
Notice the "Gates" are back! So far this is how we have seen the FAA inspectors conduct the certification procedures. It has been followed closely.
Most of this information is taken from the applicable AC's and Inspectors Handbook, but we condensed the information down to the more pertinent. If you want the full versions go to the FAA web site: http://www.faa.gov
Certifications using the Gate system
The Gate system is typically used (not always) for Part 91 Sub-K certifications. When used, it provides a logical and chronological order of the events and documents that must take place in each Phase. All the Phases must be complete to proceed to the next gate.
GATE I
Phase I Pre-Application
1. Initial contact meeting
2. Second meeting/contact
3. Formal transition meeting

Phase II Application
1. Formal application meeting
2. Submit application schedule
3. Submit required documents
4. Submit transition plan
GATE II
Phase III Document Compliance and review
- Program operating manual
- Aircraft checklist
- Inspection program
- Flight attendant manual
- Minimum equipment list
- Passenger briefing cards
- Fueling/refueling procedures
- Weight/balance control procedures
- Hazardous materials procedures
- Security procedures
- Check pilots
Review Training Curriculums:
- Hazardous materials
- Maintenance personnel
- Inspection personnel
- Ground handling/servicing
Review Contracts/Agreements/Requests:
- Owner contracts
- Training contracts
- Maintenance contracts
- Servicing contracts
- Alcohol/Drug Education
- Exemptions/deviations
Other Items:
- Final compliance statement
- Proving test plan
- Management specifications work sheet
- Training schedules
Phase IV Demonstration and Proving
- Proving Tests
- Validation Tests
- Table-top demonstrations
- Passenger handling procedures
- Monitor Flightcrew Training
- Flight Crewmember:
- Basic indoctrination
- Emergency training
- 91K transition training
- Proficiency checks
- Line checks
- Check pilot transition training
- Maintenance Training:
- Mechanics
- Inspection personnel
- Flight Attendants:
- Basic indoctrination
- Emergency training
- Competency checks
- Security
- Competency check
- Operation
- Familiarization
- Aircraft conformity inspections
- Principal base of operations inspection
- Maintenance base inspections

GATE III
Phase V. Documentation
Issue Management Specifications

These events are a close approximate as to what will take place during FAA certification. They do differ among different FSDO's and Principle Operations Inspectors.
Phase I - Preapplication.
The applicant should contact the nearest FAA Flight Standards District
Office (FSDO) and inform them of the intent to apply for Management Specifications.
You will be asked to schedule an appointment to discuss the proposed operation
and to meet with an FAA representative.
A. Initial Contact Meeting.
The FAA will use this meeting to make sure that you fully understand
the application process by providing detailed explanations of specific
requirements. Key management personnel are required to attend this meeting
and be prepared to discuss, in general terms, the plans of the proposed
operation. Many problems can be avoided by discussing all aspects of the
proposed operation and the requirements that must be accomplished before
being issued Management Specifications.
- At this meeting, FSDO personnel will brief
you on the basic information and general application requirements. If
you intend to proceed with the application process, the FSDO will give
you FAA Worksheet 8400-91K, Statement of Intent (SOI). A sample of this
worksheet and instructions for completing it are in Appendix 1. You should
complete and sign the SOI and return it to the FSDO.
- The FSDO will review the phase/gates concept
with you, as described in the Phase I flow chart shown above.
- The FSDO will then give you an application
package, which will include the following documents (or an Internet web
site where the documents can be retrieved):
- AC 91-FRACTIONAL
- Applicable sections of FAA Orders 8300.10 and 8400.10
- Fractional Ownership rule and preamble
- Preapplication Statement of Intent (SOI)
- Parts 91, 119, and 135, as applicable
- Applicable job aids and checklists
- Schedule of events that outlines the approval process
Be prepared to discuss, in general terms, the plans of your proposed
operation.
B. Second Meeting/Contact.
During the second meeting, you should be prepared to:
- Identify locations for training, maintenance, and principal base of
operations
- Submit documentation to substantiate a Fractional Ownership Program
or Business Plan (including a sample contract depicting the regulatory
requirements)
- Submit the completed SOI
- Submit proposed application schedule
- Identify management representatives
Gate and Phase NOTE: Once the FSDO has accepted everything
in the pre-application phase, you may begin Phase II.
Phase II – FORMAL Application.
The regulations state that an application for Management Specifications
shall be made in a form and manner acceptable to the FAA. You should make
a formal application by a letter that includes a request to be issued
Management Specifications to conduct operations under part 91, subpart
K. The letter should include a mailing address and indicate the full name,
title, and address of the designated agent for service, if other than
the program manager.
Figure 3-2.
You should submit the formal application a minimum of 90 days before
operations are to begin, and preferably as far in advance of the proposed
start-up date as possible. When you have fully developed the formal application,
forward it to the assigned FSDO.
The applicant will be notified by letter whether the formal application
is accepted or rejected. FAA acceptance of a formal application does not
constitute approval or acceptance of individual attachments. These documents
will be thoroughly evaluated during subsequent phases of the application
process. If the formal application is not accepted, it will be returned
with a written explanation of the reasons for its return.
SOI Processing
At this time, the FSDO will form an application team and assign an inspector
as the project manager. The project manager will be your point of contact
at the FSDO for all matters related to your application.
FSDO Team Actions
After you submit your application, the FSDO team will:
- Review the application package to confirm that it contains the required
information and attachments. If there are omissions or errors, the team
will return the formal application and all attachments to you with a
letter outlining the reasons for its return.
- Initiate electronic Management Specifications installation and training.

Figure 3-3.
Formal Application Meeting
Once the application team has reviewed your application, they will schedule
a formal application meeting. All of your key management personnel should
attend the formal application meeting. If you have a comprehensive understanding
of the requirements of part 91, subpart K, you should be able to resolve
any omissions, deficiencies, or open questions during this meeting. The
meeting will focus on the practicality of the schedule of events. The
FAA team will fully discuss and explain the subsequent phases of the application
process. You should ask for clarification of any item or event that you
do not clearly understand. The FAA project manager will not formally accept
the application during the meeting which will allow you time to resolve
any deficiencies discussed during the meeting. At the formal application
meeting, you must:
- Provide the acceptance letter that you received from the FAA following
the submission of the application.
- Submit all required programs and documents, as follows:
DOCUMENT COMPLIANCE (varies by operator)
Management Personnel Resumes and Documentation.
Program managers requesting continuous airworthiness maintenance program
(CAMP) shall provide a resume outlining the qualifications and experience
applicable management personnel. Additionally, personnel authorized to
sign MSpecs and designated as a company point of contact should be identified.
Program Operating Manual (POM).
This manual or sections of manuals contain information about your general
policies, duties, responsibilities of personnel, operational control policy,
and procedures. Part 91, subpart K requires that your manuals include
instructions and information that allow your personnel to perform their
duties and responsibilities. Section 91.1025 prescribes the content of
these manuals. You should provide a draft outline of the major parts of
all required manuals before gate II.
Program Operating Manual (POM) GENERAL
The program manager is required by section 91.1023 to prepare and keep
current a POM that sets forth procedures and policies acceptable to the
Administrator. When applicable, the manual shall contain the contents
required by section 91.1025 in enough detail so that the program manager’s
flight, ground, and maintenance personnel may properly perform their assigned
duties. During the preparation of the POM, a program manager shall ensure
that no conflict with the regulations exists that would prevent the FAA’s
acceptance of the POM.
The program manager is responsible for developing the policy and procedures
contained in the POM. The program manager must also submit it to the Administrator
for acceptance and approval, as applicable. The district office will provide
guidance to the Program Manager for developing their POM, should time
and resources be available. The district office will not draft or otherwise
prepare nor accept responsibility for developing the content of the manual.
Acceptance of the POM depends upon the program manager’s organizational
ability to develop and manage its proposed operation. Refer to the attachments
contained in Chapter 5 of this Advisory Circular for a sample program
operating manual outline and sample Destination Airport Analysis program.
(1) General Maintenance Manual. For programs that combine both part 91-K
and part 135 operations, this manual may be combined with the General
Operations Manual for part 135 Operators provided that all the required
contents for both manuals are included in the combined document and differences
in operations are clearly defined.
(2) Aircraft Maintenance Manuals/Programs.
- Inspection program
- Maintenance record keeping
- Emergency maintenance required records
(3) Weight and Balance Procedures/Program.
(4) Training Program. The training curriculum must be attached to the
formal application letter. Training curriculums must include at least
the following curriculum segments for each crewmember position:
- Basic indoctrination training
- Emergency training
- Initial aircraft ground training
- Initial aircraft flight training
- Any training programs outlined in 8400.10, applicable to part 135
operations
(5) Aircraft Flight Manual.
(6) Aircraft Operations Manual (not required for part 91, subpart K operators
who choose to use the manufacturer’s approved Aircraft Flight Manual).
(7) MEL's, if applicable.
OTHER APPROVED PROGAMS, MANUALS, AND MATERIAL.
The following is a list of additional approved programs, manuals, and
material:
- Configuration Deviation List (CDL), if applicable
- Cockpit checklist
- Passenger briefing cards
- Noise and emission plan, if applicable
- Airport Runway Analysis program (not required for non-transport category
aircraft operations)
- Exemption and deviation requests (if approved, they must be added
to the Management Specifications)
- Hazardous Materials Recognition Program
- Security Program (Coordinated with the POI, but issued by TSA)
- Flight Attendant Manual (required only for aircraft certificated to
carry more than 19 passengers or if operator chooses to carry a person
performing such duties)
- Dispatch/flight following/flight locating procedures
- Management Specifications (operations and airworthiness)
- Management Specifications worksheets
- Maintenance Reliability Program (optional)
- Proving and/or validation test plan\
- Emergency evacuation demonstration plan, if required
- Ditching demonstration plan, if required
- Continuous analysis and surveillance system for aircraft maintained
under a Continuous Airworthiness Maintenance Program (CAMP)
- Compliance statement
NOTE: On this attachment, you must list all part 91, subpart K regulations
that are applicable to your proposed operation (i.e., compliance statement).
You should identify applicable subparts and relevant sections of the subpart,
including a specific reference or a specific reference and brief description,
to a manual or other document. The brief description or reference must
describe the method of compliance for each regulation listed.
- Owner acknowledgment/contract requirements
- Flight Attendant training program curriculum and/or revisions, if
applicable
- Location of principal base of operations
- List of all DBA's the program manager may operate under
- List of aircraft
- Internal audit program
- Accident notification procedures
- Pilot safety background checks and procedures
- Location of the records repository (should be located at principal
base of operations)
- Any deviation requests
- Other requested authorizations
ACCG Creates Your Manuals & Gets FAA Approval ASAP!
Should you desire for us to make you manuals for you call 561-373-5962 or email for a quote.

|